bp pulse Electric Vehicle (EV) Charging Network Installation by TSG UK

Client Full Name: bp pulse Electric Vehicle Charging Network

Location: Staffordshire

Services: Site Design and Installation of EV Chargers

Supplier: TSG UK Solutions Ltd

The Project

As part of a larger UK-wide contract, bp pulse required the installation of ultra-fast chargers at its Staffordshire site.

TSG UK Solutions was awarded the contract at the appraisal stage, via the fixed Global Framework Agreement (GFA) established with bp pulse.  TSG conducted a comprehensive site survey to collect essential data, followed by a power feasibility study to evaluate the project’s viability. Based on these findings, TSG developed a proof of concept (POC).

Once the POC was accepted, TSG moved to the design and development phase, when detailed plans and designs were created, including the critical electrical design component. TSG’s project manager (PM) handled the entire planning process, advising bp pulse on recommended council surveys and traffic management solutions.

The Solution

bp pulse decided to install ultra-fast Alpitronic HYC 300 HV chargers offering six charging points. This installation required civil works and the laying of cables. TSG’s electrical estimation team provided a final quotation that included the supply and installation of chargers, design, construction, contestable works, application of power, grid connection and commissioning.

The site then transitioned into the construction phase and the project’s implementation. The dedicated PM worked closely with bp pulse and the relevant TSG teams in design, estimation, operations and street works, to ensure a swift execution of the installation.

The Result

All three chargers are now fully operational, and bp pulse is extremely pleased with TSG’s working practices, the delivery timescale and the final result.

Since the initial installation, TSG has secured the installation and commissioning of six additional sites. Once these are energised, the total number of completed EV charging sites for bp pulse will reach 76

TSG’s partnership with bp pulse is moving from strength to strength, as the EV charge specialist advances toward achieving net zero across its entire operation by 2050 or sooner.

For more information, contact TSG UK

Tel:      0333 015 3001

Email:  enquiries.uk@tsg-solutions.com

Swift Sharma bp pulse charger front panel
Swift Sharma bp pulse canopy and MID
Swift Sharma bp pulse charger inside unit
Swift Sharma bp pulse charge and battery unit