H.T. Transport & Spedition A/S
H.T. Transport & Spedition A/S is a family-owned transport and logistics company, founded in Billund in 1973 by Henning Toftlund Hansen. The company mainly handles industrial goods and air freight, with distribution services in Denmark and export transport to and from Switzerland.
HT Transport has 70 lorries, ten of which are now electric. The company decided to switch to electric vehicles because it feels a responsibility towards the environment. Co-owner Niclas Bay-Smidt Toftlund puts it this way:
“We clearly have a responsibility towards the environment, because we operate lorries that emit a lot of CO₂ and run on diesel. That is why we also need to try to think more long-term.”
The experience with the first electric lorries has been positive, both for the drivers and in the workshop.
The drivers who drive the electric lorries are happy with them. My impression is that they wouldn’t want to go back to the old ones. They don’t feel as mentally drained when driving an electric lorry. There’s less noise, and they’re not as knackered in the evening as they otherwise would be. And there are fewer repairs.
With the introduction of electric lorries came the need for on-site charging facilities capable of keeping up with a working day during which lorries arrive and depart at various times.
TSG has supplied fast-charging facilities to HT Transport’s depot in Billund, designed for heavy-duty electric lorries. The lorries do not charge at a fixed time in the afternoon. They are connected as and when they arrive at the depot throughout the day, so the charging system must be ready at all times and able to charge several lorries simultaneously. The charging facility came into operation in March 2025.
In the video, co-owner Niclas Bay-Smidt Toftlund himself talks about HT Transport and the project at the site in Billund.
TSG has supplied and installed a 600 kW charging system from Kempower with four charging points. A single power unit supplies all four charging points, allowing several lorries to be connected at the same time. The backend software manages dynamic load balancing, ensuring that the highest available charging power is always delivered to each point.
This fits in with the way HT Transport operates. The driver plugs in the lorry when it returns from a journey, between loading and unloading, and the system manages the number of vehicles currently in the yard. There is no fixed charging window to plan the day around.
Read more about commercial charging points and heavy goods transport.
Through its collaboration with TSG on charging, HT Transport entered into discussions with NRGreen, TSG’s Danish energy company, regarding a battery storage facility. Battery storage was not an area in which the company had any experience, so NRGreen drew up a business case to assess whether such a facility would be viable. Based on this, HT Transport opted for a 375 kW / 1,560 kWh system, which NRGreen will install and connect to the grid.
The battery has two functions. It is designed to optimise the cost of electricity for HT Transport’s own consumption, and to generate revenue on the market for system services and electricity trading. At full capacity, it can supply power for just over four hours. The chargers have their own electricity meters and are separate from the battery.
Read NRGreen’s case study on the battery system at HT Transport
HT Transport’s electric lorries are charged at the depot as part of the normal working day. With four charging points on a single system, several lorries can be charged at the same time, and drivers plug them in when they get home, rather than having to wait for a specific time.
“We’ve had a really good working relationship with TSG and NRGreen.”