As part of a larger UK-wide contract, bp pulse required the installation of ultra-fast chargers at its Staffordshire site. TSG UK Solutions was awarded the contract at the appraisal stage, via the fixed Global Framework Agreement (GFA) established with bp pulse. We conducted a comprehensive site survey to collect essential data, followed by a power feasibility study to evaluate the project’s viability. Based on these findings, we developed a proof of concept (POC).
Once the POC was accepted, we moved to the design and development phase, when detailed plans and designs were created, including the critical electrical design component. TSG’s project manager (PM) handled the entire planning process, advising bp pulse on recommended council surveys and traffic management solutions.